Project Management Calculators
Free calculators for earned value (CV, SV, CPI, SPI, EAC, ETC, VAC, TCPI), PERT three-point estimates, critical path and float, ROI and payback, and project budgets with reserves. Every result shows the formula behind it, so you can check your working for the PMP or CAPM exam or on a live project.
How to use each calculator
- Earned value (EVM): enter BAC, PV, EV and AC. CPI or SPI below 1.0 means over budget or behind schedule. Pick the EAC that matches the situation: BAC ÷ CPI when current cost performance will continue, AC + (BAC − EV) when the variance was a one-off, and AC + (BAC − EV) ÷ (CPI × SPI) when both cost and schedule drive the forecast.
- PERT estimate: enter optimistic, most likely and pessimistic values. The beta (PERT) mean weights the most likely value four times; the triangular mean weights all three equally. Standard deviation is (P − O) ÷ 6.
- Critical path and float: list activities with durations and finish-to-start predecessors. The calculator runs the forward and backward pass and shows ES, EF, LS, LF, total float and free float. Activities with zero total float are on the critical path.
- ROI and payback: enter the initial investment and the net cash inflow for each period. ROI = (gain − cost) ÷ cost. Payback is the point where cumulative cash flow turns positive. Neither accounts for the time value of money.
- Budget and reserves: add work package estimates, then contingency reserve for identified risks to get the cost baseline. Add management reserve for unidentified risks to get the total project budget. The cost baseline is what earned value is measured against.
Exam tips
- On the PMP exam, questions usually give you the inputs and ask you to interpret the result, for example what a CPI of 0.9 says about the project, rather than only to calculate it.
- Variances: negative is bad, positive is good. Indexes: below 1.0 is bad, above 1.0 is good. TCPI is the exception: above 1.0 means the remaining work must be done more efficiently.
- Management reserve is not part of the cost baseline, so it is not included in BAC.
Worked examples: reading the results like an exam question
The calculator opens with a sample project: BAC 100,000, PV 50,000, EV 45,000 and AC 48,000. Here is how to read every result, the way a PMP question expects you to.
Earned value walkthrough
- Cost variance (CV) = EV − AC = −3,000. You have spent 3,000 more than the value of the work completed. Negative means over budget.
- Schedule variance (SV) = EV − PV = −5,000. You have completed 5,000 less work than planned by now. Negative means behind schedule.
- CPI = EV ÷ AC = 0.94. Each dollar spent is producing about 94 cents of planned value.
- SPI = EV ÷ PV = 0.90. Work is progressing at 90% of the planned rate.
- EAC (typical) = BAC ÷ CPI ≈ 106,667. Use this when the current cost performance is expected to continue.
- EAC (atypical) = AC + (BAC − EV) = 103,000. Use this when the overrun was a one-off and the rest of the work will go to plan.
- EAC (CPI × SPI) = AC + (BAC − EV) ÷ (CPI × SPI) ≈ 113,185. Use this when both cost and schedule problems will keep affecting the remaining work.
- ETC = EAC − AC ≈ 58,667 (using the typical EAC). This is what you still expect to spend.
- VAC = BAC − EAC ≈ −6,667. You expect to finish about 6,667 over budget.
- TCPI = (BAC − EV) ÷ (BAC − AC) ≈ 1.06. To finish on the original budget, the remaining work must be done 6% more efficiently than planned. Anything well above 1.0 is a warning that the budget is unrealistic.
PERT example
An activity has an optimistic estimate of 4 days, most likely 6 and pessimistic 14. The beta (PERT) estimate is (4 + 4×6 + 14) ÷ 6 = 7 days. The standard deviation is (14 − 4) ÷ 6 ≈ 1.67 days. A triangular estimate would be (4 + 6 + 14) ÷ 3 = 8 days. If a question says "PERT" or "beta", use the weighted formula.
Critical path example
Path A–B–D takes 3 + 4 + 5 = 12 days and path A–C–D takes 3 + 2 + 5 = 10 days. The critical path is the longest path, A–B–D, so the project takes 12 days. Activity C has 2 days of total float: it can slip 2 days without delaying the project. Activities on the critical path have zero float.
ROI and payback example
A project costs 50,000 and returns benefits of 80,000. ROI = (80,000 − 50,000) ÷ 50,000 = 60%. If the benefits arrive at 12,500 a year, the payback period is 50,000 ÷ 12,500 = 4 years. On the exam, a shorter payback period and a higher ROI are better, but net present value (NPV) beats both when the question gives it, because it accounts for the time value of money.
Reserves example
Contingency reserves cover identified risks and sit inside the cost baseline. Management reserves cover unknown risks and sit outside the baseline but inside the total project budget. The project manager can usually use contingency reserves; using management reserves typically needs sponsor or management approval.
Frequently asked questions
Which EAC formula should I use on the PMP exam?
Read the scenario. If it says the variance will continue, use BAC ÷ CPI. If it says the variance was a one-time event, use AC + (BAC − EV). If both cost and schedule performance will affect the rest of the project, use the CPI × SPI version.
What does a TCPI above 1.0 mean?
The remaining work has to be done more efficiently than the work so far. The further above 1.0, the less likely it is that the project will finish on budget.
Do I need to memorise these formulas for the exam?
Yes. You won't get a formula sheet in the exam. Formula questions are a small share of the exam, but they are some of the easiest marks to secure with practice.
Keep learning
- PMP formula cheat sheet: every formula on one page, with when to use each.
- Decision Lab: practice the judgment behind situational questions.
- Free mock exam: 50 timed questions to see where you stand.
- Certification guides: eligibility, exam format and renewal, from official sources.
Last reviewed: October 8, 2026. Formulas follow standard PMI earned value and scheduling conventions as taught for the PMP exam.