PMP Formula Cheat Sheet

All 18 PMP formulas, explained in plain English

This cheat sheet covers every formula you're likely to need for the PMP exam. Below, each one is listed with what it tells you and when to use it, so you can revise without the interactive sheet.

Key terms

  • PV (planned value): the value of the work scheduled to be done by now.
  • EV (earned value): the value of the work actually completed.
  • AC (actual cost): what the completed work actually cost.
  • BAC (budget at completion): the total approved budget.
  • EAC (estimate at completion): what the project is now expected to cost in total.

Earned value: where does the project stand?

  • Cost variance (CV) = EV − AC. Negative means over budget.
  • Schedule variance (SV) = EV − PV. Negative means behind schedule.
  • Cost performance index (CPI) = EV ÷ AC. Below 1 means over budget.
  • Schedule performance index (SPI) = EV ÷ PV. Below 1 means behind schedule.
  • Estimate to complete (ETC) = EAC − AC. What you still expect to spend from today.
  • Variance at completion (VAC) = BAC − EAC. Negative means a projected overrun.

Forecasting: which EAC formula?

  • EAC = BAC ÷ CPI when current cost performance is expected to continue.
  • EAC = AC + (BAC − EV) when the overrun was a one-off and the original plan will resume.
  • EAC = AC + bottom-up ETC when the original estimate was fundamentally wrong and you need a new one.
  • EAC = AC + (BAC − EV) ÷ (CPI × SPI) when schedule pressure will also affect cost.
  • To-complete performance index (TCPI) = (BAC − EV) ÷ (BAC − AC). The CPI you need from now on to finish on budget. Above 1 is harder. To hit a new EAC instead, divide by (EAC − AC).

Exam tip: the question usually tells you which EAC to use. Words like "this trend will continue" point to BAC ÷ CPI. Words like "a one-time problem" point to AC + (BAC − EV).

Scheduling and estimating

  • Total float = LS − ES = LF − EF. How long an activity can slip without delaying the project. Activities on the critical path have zero float.
  • PERT (beta) estimate = (O + 4M + P) ÷ 6. Weights the most likely estimate.
  • Triangular estimate = (O + M + P) ÷ 3. A simple average of the three estimates.
  • Standard deviation (PERT) = (P − O) ÷ 6. A larger value means more uncertainty in the estimate.

Communication, risk and finance

  • Communication channels = n(n − 1) ÷ 2, where n includes you. A team of 10 has 45 channels; adding 2 people takes it to 66.
  • Expected monetary value (EMV) = probability × impact. Threats are negative and opportunities positive. A 20% chance of a 50,000 loss has an EMV of −10,000.
  • Present value = FV ÷ (1 + r)ⁿ. Money in the future is worth less today. 110,000 received in one year at 10% is worth 100,000 now.

How to learn the formulas quickly

  1. Learn the five key terms first. Every earned value formula is built from them.
  2. Remember the pattern: CV and SV subtract, CPI and SPI divide. A negative variance or an index below 1 is bad news.
  3. Practise with real numbers in our project management calculators, which show the formula behind every result.
  4. Do a few timed formula questions each week rather than cramming them at the end.

Frequently asked questions

How many formula questions are on the PMP exam?

PMI doesn't publish a number, and formula questions are a small part of the exam. Most marks come from scenario-based judgment questions, which you can practise in Decision Lab.

Do you get a formula sheet in the exam?

No. You need to know the formulas from memory. An on-screen calculator is available.

Which formulas matter most?

CPI, SPI, CV, SV, the four EAC formulas, float and PERT come up most often in practice questions. Learn those first.