top of page
PM Exam Lab logo, PMP exam prep

PMP Earned Value Formulas Explained (With Worked Examples)

Oct 7
3 min read

Updated: Oct 29

Earned value management (EVM) questions show up on the PMP exam, and they're some of the easiest points to win if you know the formulas and what the results mean. The current exam focuses more on reading the results than on long calculations, so understanding beats memorizing.

The three building blocks

Every EVM formula uses these three values:

  • Planned Value (PV): the budgeted cost of the work that should be done by now.

  • Earned Value (EV): the budgeted cost of the work that is actually done.

  • Actual Cost (AC): what you have actually spent on that work.

You also need the Budget at Completion (BAC): the total budget for the whole project.

Variances: are we ahead or behind?

  • Cost Variance: CV = EV - AC

  • Schedule Variance: SV = EV - PV

A negative number is bad news: over budget, or behind schedule. A positive number is good news.

Performance indexes: how efficient are we?

  • Cost Performance Index: CPI = EV / AC

  • Schedule Performance Index: SPI = EV / PV

Less than 1 is bad. More than 1 is good. Exactly 1 is on plan.

Forecasts: where will we end up?

  • Estimate at Completion (typical case): EAC = BAC / CPI

  • Estimate to Complete: ETC = EAC - AC

  • Variance at Completion: VAC = BAC - EAC

  • To-Complete Performance Index: TCPI = (BAC - EV) / (BAC - AC)

TCPI tells you how efficiently you must work from now on to finish within the original budget. A TCPI above 1 means you have to do better than you planned.

Worked example

A project has a budget (BAC) of $100,000. By today you planned to finish 50% of the work, but you've finished 40%, and you've spent $45,000.

  • PV = 50% x $100,000 = $50,000

  • EV = 40% x $100,000 = $40,000

  • AC = $45,000

  • CV = 40,000 - 45,000 = -$5,000 (over budget)

  • SV = 40,000 - 50,000 = -$10,000 (behind schedule)

  • CPI = 40,000 / 45,000 = 0.89

  • SPI = 40,000 / 50,000 = 0.80

  • EAC = 100,000 / 0.889 = $112,500

  • VAC = 100,000 - 112,500 = -$12,500

What it means: the project is behind schedule and over budget. At the current cost efficiency, it will finish about $12,500 over budget.

The other three EAC formulas

BAC / CPI assumes today's cost efficiency will continue. The exam also tests three other versions. Using the same project (BAC $100,000, EV $40,000, AC $45,000, CPI 0.89, SPI 0.80):

  • One-off variance: EAC = AC + (BAC - EV) = 45,000 + 60,000 = $105,000

  • Cost and schedule both affect the remaining work: EAC = AC + (BAC - EV) / (CPI x SPI) = 45,000 + 60,000 / 0.711 = $129,375

  • Original estimate was flawed: EAC = AC + a new bottom-up ETC

And finishing the example: ETC = 112,500 - 45,000 = $67,500 still to spend. TCPI = (100,000 - 40,000) / (100,000 - 45,000) = 1.09, so the team must now work 9% more efficiently to stay on the original budget.

How to pick the right EAC on the exam

Read the wording of the scenario, not the numbers:

  1. "Current performance will continue" → BAC / CPI

  2. "The variance was a one-time event" → AC + (BAC - EV)

  3. "The deadline is fixed" or "both cost and schedule matter" → AC + (BAC - EV) / (CPI x SPI)

  4. "The original estimate was wrong" → AC + bottom-up ETC

Three traps the exam loves

  • TCPI flips the rule. For every other index, above 1 is good. For TCPI, above 1 means the job just got harder.

  • Using PV where EV belongs. PV only appears in SV and SPI.

  • Calculating when you only need to interpret. If SPI is 0.8, you're behind. Don't spend two minutes proving it.

Three memory tricks

  1. EV always comes first in variance and index formulas.

  2. C goes with AC (cost), S goes with PV (schedule).

  3. Negative or less than 1 = bad. Positive or more than 1 = good.

What the exam really wants

On a situational question, the number is only step one. If the CPI is 0.89, the best answer usually isn't "cut the budget." It's to find out why, review the cause with the team, and follow the right process to correct course.

Get all 18 formulas on one page, with plain-English notes on when to use each.

Ready to test yourself on real exam-style questions? Take the free PMP mock exam

Comments


bottom of page
WhatsApp us