PMP Earned Value Formulas Explained (With Worked Examples)
Updated: Oct 29
Earned value management (EVM) questions show up on the PMP exam, and they're some of the easiest points to win if you know the formulas and what the results mean. The current exam focuses more on reading the results than on long calculations, so understanding beats memorizing.
The three building blocks
Every EVM formula uses these three values:
Planned Value (PV): the budgeted cost of the work that should be done by now.
Earned Value (EV): the budgeted cost of the work that is actually done.
Actual Cost (AC): what you have actually spent on that work.
You also need the Budget at Completion (BAC): the total budget for the whole project.
Variances: are we ahead or behind?
Cost Variance: CV = EV - AC
Schedule Variance: SV = EV - PV
A negative number is bad news: over budget, or behind schedule. A positive number is good news.
Performance indexes: how efficient are we?
Cost Performance Index: CPI = EV / AC
Schedule Performance Index: SPI = EV / PV
Less than 1 is bad. More than 1 is good. Exactly 1 is on plan.
Forecasts: where will we end up?
Estimate at Completion (typical case): EAC = BAC / CPI
Estimate to Complete: ETC = EAC - AC
Variance at Completion: VAC = BAC - EAC
To-Complete Performance Index: TCPI = (BAC - EV) / (BAC - AC)
TCPI tells you how efficiently you must work from now on to finish within the original budget. A TCPI above 1 means you have to do better than you planned.
Worked example
A project has a budget (BAC) of $100,000. By today you planned to finish 50% of the work, but you've finished 40%, and you've spent $45,000.
PV = 50% x $100,000 = $50,000
EV = 40% x $100,000 = $40,000
AC = $45,000
CV = 40,000 - 45,000 = -$5,000 (over budget)
SV = 40,000 - 50,000 = -$10,000 (behind schedule)
CPI = 40,000 / 45,000 = 0.89
SPI = 40,000 / 50,000 = 0.80
EAC = 100,000 / 0.889 = $112,500
VAC = 100,000 - 112,500 = -$12,500
What it means: the project is behind schedule and over budget. At the current cost efficiency, it will finish about $12,500 over budget.
The other three EAC formulas
BAC / CPI assumes today's cost efficiency will continue. The exam also tests three other versions. Using the same project (BAC $100,000, EV $40,000, AC $45,000, CPI 0.89, SPI 0.80):
One-off variance: EAC = AC + (BAC - EV) = 45,000 + 60,000 = $105,000
Cost and schedule both affect the remaining work: EAC = AC + (BAC - EV) / (CPI x SPI) = 45,000 + 60,000 / 0.711 = $129,375
Original estimate was flawed: EAC = AC + a new bottom-up ETC
And finishing the example: ETC = 112,500 - 45,000 = $67,500 still to spend. TCPI = (100,000 - 40,000) / (100,000 - 45,000) = 1.09, so the team must now work 9% more efficiently to stay on the original budget.
How to pick the right EAC on the exam
Read the wording of the scenario, not the numbers:
"Current performance will continue" → BAC / CPI
"The variance was a one-time event" → AC + (BAC - EV)
"The deadline is fixed" or "both cost and schedule matter" → AC + (BAC - EV) / (CPI x SPI)
"The original estimate was wrong" → AC + bottom-up ETC
Three traps the exam loves
TCPI flips the rule. For every other index, above 1 is good. For TCPI, above 1 means the job just got harder.
Using PV where EV belongs. PV only appears in SV and SPI.
Calculating when you only need to interpret. If SPI is 0.8, you're behind. Don't spend two minutes proving it.
Three memory tricks
EV always comes first in variance and index formulas.
C goes with AC (cost), S goes with PV (schedule).
Negative or less than 1 = bad. Positive or more than 1 = good.
What the exam really wants
On a situational question, the number is only step one. If the CPI is 0.89, the best answer usually isn't "cut the budget." It's to find out why, review the cause with the team, and follow the right process to correct course.
Get all 18 formulas on one page, with plain-English notes on when to use each.
Ready to test yourself on real exam-style questions? Take the free PMP mock exam


Comments