How to Solve Critical Path Questions on the PMP, Step by Step

Oct 29
4 min read

Updated: Nov 8

Short answer: Draw the network, run a forward pass to find each activity's earliest dates, run a backward pass to find the latest dates, then subtract to get float. Activities with zero total float form the critical path, and the longest path through the network sets the project duration.

What the PMP asks about the critical path

Critical path questions test whether you can read a schedule network and reason about it. Typical questions ask you to find the project duration, name the critical path, calculate float for one activity, or say what happens to the end date if an activity is delayed.

There is no formula sheet, but you get an on-screen calculator. The arithmetic is simple, so a consistent method matters more than speed.

The key terms

  • ES (early start): the earliest an activity can begin.

  • EF (early finish): ES plus duration.

  • LS (late start): the latest an activity can begin without delaying the project.

  • LF (late finish): LS plus duration.

  • Total float: LS minus ES (or LF minus EF). How long an activity can slip without delaying the project end date.

  • Free float: how long an activity can slip without delaying the early start of any successor.

Our PMP formula cheat sheet lists these alongside the other formulas worth memorizing.

A worked example

Here is an example network. Durations are in days.

  • A: 3 days, no predecessor

  • B: 4 days, after A

  • C: 2 days, after A

  • D: 5 days, after B

  • E: 6 days, after C

  • F: 2 days, after D and E

Sketch it first. A splits into two paths, B-D and C-E, which merge into F.

Step 1: list the paths

  • A-B-D-F: 3 + 4 + 5 + 2 = 14 days

  • A-C-E-F: 3 + 2 + 6 + 2 = 13 days

The longest path is A-B-D-F at 14 days. That is the critical path, and 14 days is the project duration.

Step 2: forward pass

Start at zero and work left to right. EF = ES + duration. When an activity has more than one predecessor, its ES is the largest predecessor EF.

  • A: ES 0, EF 3

  • B: ES 3, EF 7

  • C: ES 3, EF 5

  • D: ES 7, EF 12

  • E: ES 5, EF 11

  • F: ES 12 (the larger of 12 and 11), EF 14

Step 3: backward pass

Start at the end with LF equal to the project finish, 14, and work right to left. LS = LF minus duration. When an activity has more than one successor, its LF is the smallest successor LS.

  • F: LF 14, LS 12

  • D: LF 12, LS 7

  • E: LF 12, LS 6

  • B: LF 7, LS 3

  • C: LF 6, LS 4

  • A: LF 3 (the smaller of 3 and 4), LS 0

Step 4: calculate float

Total float = LS minus ES.

  • A: 0 minus 0 = 0

  • B: 3 minus 3 = 0

  • C: 4 minus 3 = 1

  • D: 7 minus 7 = 0

  • E: 6 minus 5 = 1

  • F: 12 minus 12 = 0

A, B, D and F have zero float, which confirms the critical path from Step 1. C and E each have 1 day of total float, which matches the gap between the two paths (14 minus 13).

Free float shows a subtle point. C's free float is E's ES minus C's EF: 5 minus 5 = 0. E's free float is F's ES minus E's EF: 12 minus 11 = 1. So the one day of float on that path is shared. If C slips by a day, E starts a day later and uses up the float, and E then has none left.

Common question twists

  • "Activity E is delayed 3 days. What is the new duration?" E has 1 day of float, so 2 days pass through to the end. The path A-C-E-F becomes 16 days, and the project now takes 16 days with a new critical path.

  • "Activity C is delayed 1 day." It has 1 day of total float, so the end date does not move, but the path becomes critical.

  • Day-one convention. Some sources start the first activity on day 1 instead of day 0. Then EF = ES + duration minus 1, and the next activity starts on EF + 1. Both methods give the same duration and float. Stay consistent.

  • Negative float. If a required finish date is earlier than the calculated finish, float comes out negative. That means the schedule cannot meet the date without compression, such as crashing or fast tracking.

To check your own practice networks, try the critical path and float tool in our PM calculators.

Frequently asked questions

Can there be more than one critical path?

Yes. If two paths tie for the longest duration, both are critical. That raises schedule risk because a delay on either one delays the project.

Do I need the forward and backward pass if I can just add up paths?

Adding up paths finds the duration and critical path quickly. You still need the passes when a question asks for a specific ES, LF, or free float.

How much of the exam is critical path math?

PMI does not publish how many questions cover any specific calculation. Expect calculations to be a small part of the exam, with most questions being situational.

Should I memorize the formulas?

Yes. There is no formula sheet, so know EF = ES + duration, LS = LF minus duration, and total float = LS minus ES. Our guide to PMP earned value formulas covers the other calculations.

Test yourself under exam conditions

Take the free 50-question PMP mock exam to practice calculations alongside situational questions and see your domain scores.

Exam details change, so always confirm current requirements on pmi.org.